How much should a last time buy cover, and when should a discontinued part be remade to print?

Short answer

A last time buy is the final order you place for a part before its source stops making it, sized to carry your production and service needs until the part is no longer needed or until a replacement source, a remade-to-print part or a redesign is ready. It should cover forecast demand to that end point plus spares, yield loss and a margin for forecast error, and a part should be remade to print instead when you own a complete drawing and the right to use it, the remaining need is long or uncertain, and holding years of stock costs more than qualifying a new source.

By Saola Manufacturing engineering team · Published · Updated

The problem usually arrives as a short letter or an email from a purchasing contact: a supplier is closing a line, dropping a process, retiring a worn die or leaving the business, and you have a window to place a final order. Most published material on last time buys is written for electronic components, where a manufacturer discontinues a catalog part and a whole industry of databases tracks it. A custom machined, cast or stamped part is different. Nobody else stocks it, the drawing may not describe everything the old supplier actually did, and the tooling may belong to someone who is about to disappear. This guide is for the design engineer, the supply chain manager and the buyer who have to decide two things fast: how many to buy, and whether to start remaking the part elsewhere while there is still a good supplier and good parts to copy. It is general engineering and purchasing guidance; your contracts decide who owns what.

On this page

How do you know a custom part is heading for a last time buy?

The clear signal is a written discontinuance or last-order notice from the supplier. The earlier signals are a declined quote, a sudden price jump, a request to accept a different material or process, and tooling that needs repair more often.

Obsolescence specialists call the general problem DMSMS, diminishing manufacturing sources and material shortages: losing, or being about to lose, the makers or suppliers of an item or of the material it is made from. SAE STD0016A sets out how an OEM documents its plan for handling it. For a custom metal part the warning signs are rarely a formal notice. Watch for a supplier that no-quotes a repeat order, quotes it only with a long list of exceptions, asks to change the alloy or bar size because a mill has dropped it, asks to move the work to another plant, or tells you a die or fixture needs major repair before the next run. Each of these means the current source may not exist for the remaining life of your product.

Treat the first warning as the start of the clock, not the formal letter. Once the notice is issued you have one order left and no leverage. Before it is issued you can still ask for samples, measurement data, process records and the return of your tooling, and you can still place a trial order with a second source while the original parts remain available as the reference.

Once a notice or a strong warning arrives, work through these steps before you argue about quantity:

  1. Get the dates in writing. The last date you can order, the last date the supplier will ship, and whether it will hold a final lot and release it against scheduled deliveries or ship it all at once.
  2. List what belongs to you. Tooling, fixtures, special gauges and any samples you paid for. Ask separately about CNC programs, process sheets and inspection plans; these are often the supplier’s own work, so ask what it will release and on what terms.
  3. Capture the last good parts. Have retained parts from the most recent accepted lots measured against every drawing callout, keep several as physical references, and collect the material certificates and inspection records for those lots. Some aerospace buyers formalize this as a last article inspection before production moves.
  4. Count real demand and stock. Production, service and your own losses, as in the worksheet below, and only stock that has been inspected.
  5. Start the second source in parallel. Send the RFQ for a remake while the original supplier is still running, so a bad first article does not leave you without parts.
  6. Plan storage and identification. Label the last time buy stock with part number, revision and lot, protect it from corrosion, and decide who may draw from it.

Why do suppliers discontinue custom metal parts?

In rough order of how often buyers meet them: low or irregular volume that no longer pays for setups, a supplier exiting a process or closing, a worn tool nobody wants to fund, and a material grade or purchased component that is no longer made.

  • Volume falls below the supplier’s threshold. A part that once ran every month now runs once a year. The setup, fixture storage and first-piece inspection cost the same, so the supplier drops it or prices it out.
  • The supplier exits the process or the business. A shop sells a machine, a foundry stops a pouring line, a finisher closes a tank, or the company is acquired and the new owner pares the product range.
  • Tooling reaches the end of its life. A die casting die or a progressive stamping die wears out, and the question of who pays for a new one exposes that ownership was never written down. The tooling ownership guide covers how to settle that.
  • Material or a bought-in component disappears. A mill discontinues a grade, temper or bar size, or a purchased insert, seal or fastener in an assembly is withdrawn.
  • Regulation or trade rules change. A restricted substance in a coating, or a tariff that makes the current country of origin uneconomic, can end a source as surely as a closure.

The cause matters because it changes the fix. A volume problem can sometimes be solved by consolidating several low-volume parts with one supplier or by ordering in larger, less frequent lots. A closure or a dead tool cannot; there you choose between buying ahead and remaking the part.

How do you calculate how much a last time buy should cover?

Add remaining production demand to the chosen end date, service and spares demand, your own yield loss and a margin for forecast error, then subtract stock you already hold or have on order. The end date is either the end of product support or, for a bridge buy, the date a new source will be qualified.

Start by choosing the end date, because it drives everything else. Obsolescence researchers at the University of Maryland define a lifetime buy (also called a life-of-type buy) as one sized to meet current and expected future demand, and a bridge buy as one sized only to reach the next redesign (Feng, Singh and Sandborn, 2007). Writing about electronic systems, Sandborn noted that in hindsight programs often would have avoided more cost by bridge-buying parts to a single planned redesign date than by resolving each obsolete part to the end of the system’s field life, while cautioning that this is not the best approach for every system (DSP Journal, 2008). The same reasoning carries over to a single custom part: if you can realistically qualify a new source, buy only to that date.

Then build the quantity from separate lines rather than one guess. Production demand comes from the build plan to the end date. Service demand comes from the installed base and the observed replacement rate, which your field returns or spare-parts sales history will show better than any forecast. Add the parts your own process consumes, such as assembly scrap, test failures and parts pulled for audits. Finally add a margin for uncertainty, which grows with the length of the period you are covering.

The margin is a cost trade, not a matter of taste. The same Maryland work breaks the cost of a lifetime buy into procurement, inventory, disposal and penalty (shortage) costs. Every part you buy and never use costs its price plus years of storage and tied-up capital, and may end as scrap. Every part you are short costs whatever a line stop, an emergency redesign or a lost service contract costs. Standard inventory theory for one-time buys (the newsvendor model) sets the target probability of not running short at the shortage cost divided by the sum of the shortage cost and the excess cost, so a part whose shortage would stop a product line justifies a much larger margin than a cosmetic bracket. Two practical checks keep the result honest: confirm the supplier can actually make the quantity before the window closes, and check how the parts will survive storage. Unprotected carbon steel rusts and some coatings age, so specify packaging, preservation and periodic inspection for the stock as part of the buy.

Last time buy sizing worksheet · general industry guidance; obsolescence management planning per IEC 62402:2019 and SAE STD0016A (2023); lifetime-buy cost elements per Feng, Singh and Sandborn, 2007
LineWhere the figure comes fromCommon mistake
End dateEnd of product support (lifetime buy) or the planned qualification date of a new source (bridge buy)Defaulting to end of support when a second source is realistic
Production demandBuild plan to the end date, by yearUsing last year’s run rate for a product already in decline
Service and spares demandInstalled base times observed replacement rate, from returns and spares historyForgetting spares entirely because production planning owns the buy
Own yield lossAssembly scrap, test failures, audit and destructive-test pullsAssuming every purchased part becomes a shipped product
Uncertainty marginShortage cost versus excess cost (one-time-buy inventory logic)A flat margin applied to every part regardless of criticality
Less: stock and open ordersOn hand, in transit, at the supplier, and parts recoverable from returnsCounting stock that has not been inspected or has aged in storage
Storage planPackaging, preservation, location and re-inspection interval for the stockBuying the quantity but not budgeting how to keep it usable

Should you make a last time buy, a bridge buy, or remake the part to print?

Make a full last time buy when the remaining need is short, predictable and cheap to store. Bridge buy and remake to print when the need is long or uncertain, the part is expensive to hold, and you own a drawing complete enough for another supplier to make it.

The decision turns on four questions. How long is the remaining need, and how sure are you of it? What does a year of storage cost compared with qualifying a new source? Do you hold a drawing and the rights to have someone else make the part? And is the tooling yours and recoverable? If the answers are short, certain, cheap and no, buy to the end and close the file. If they are long, uncertain, expensive and yes, start a remake now and buy only enough to bridge to it.

Rights matter more than buyers expect. Government contracting draws the line sharply: the US defense acquisition rules give the government only limited rights in some technical data, and with limited rights it may not use the data for manufacture or let another party use it without permission (DFARS 252.227-7013). Commercial contracts vary, but the question is the same. If the part is the supplier’s own design that you bought by catalog number, you may need its permission or a new design of your own. If it is built to your drawing, you can usually take that drawing elsewhere.

Resolution options for a discontinued custom part · general industry guidance; data rights per DFARS 252.227-7013 (48 CFR, 2025)
OptionFits whenMain risk
Lifetime (last time) buyRemaining need is short and predictable; part is small, stable and cheap to storeOverbuy that ends as scrap, or underbuy with no source left
Bridge buy plus remake to printYou own a complete drawing and the rights; need is long or uncertainNew source misses an undocumented feature the old supplier controlled
Transfer the toolingCast or stamped part; tooling is yours and in usable conditionTool will not run on the new plant’s machine without rework
Reverse engineer from samplesNo usable drawing exists, but good parts and function knowledge doMeasured parts give sizes, not the tolerances the function needs
Redesign or substituteThe product is being refreshed anyway, or the part was over-specifiedRequalification cost and time at the system level

What do you need before a discontinued part can be remade to print?

A drawing and model that fully define the part, the right to use them, the material and finish specifications, a set of good reference parts with their measurements, and either the original tooling or a plan and budget for new tooling.

Check the drawing against reality before the old supplier is gone. Drawing practice under ASME Y14.100, with dimensioning and tolerancing per ASME Y14.5, expects the drawing to define every feature completely enough that another shop could make the part from it. In practice, long-running parts drift away from their prints. The old supplier may have added a chamfer to stop a burr, adjusted a casting to fill better, used a specific plating thickness that the drawing leaves open, or worked under a deviation that never became a revision. Pull retained samples from recent good lots, measure them against every callout, and record where the parts and the drawing disagree. Ask the supplier for its process records, inspection data, material certificates and any approved deviations while it still has a reason to cooperate.

Where the drawing is missing or unusable, reverse engineering from samples can recover the geometry, and a material analysis and hardness check can recover the alloy and condition. What measurement cannot recover is the tolerance the function needs, so an engineer has to set it from the mating parts and the use, not from the spread of a few samples. Treat the result as a new drawing at a new revision.

Plan for qualification. In aerospace, AS9102 calls for a full first article inspection, or a partial one covering the affected characteristics, when the manufacturing source, location of manufacture, process, tooling or material changes in a way that can affect fit, form or function. Moving a discontinued part to a new supplier is exactly that kind of change, and the same discipline works in any industry. Ask for a ballooned first article report against the current revision, compare it with your reference samples, and test-fit the parts in the assembly before you let the last time buy stock run down. The first article inspection guide lists what that report should contain.

What should the drawing, RFQ and purchase order say so the next discontinuance is not a surprise?

Write in a discontinuance notice and last-order window, state who owns the drawings, models and tooling, require the supplier to keep and hand over process and inspection records, and keep your drawing at the revision the parts are actually made to.

  • Notice and last-order window. The supplier gives written notice before it stops making a part, and you get a stated period to place a final order. Agree the period in your terms rather than leaving it to goodwill.
  • Ownership. Drawings, models, specifications and tooling paid for by you are your property, are identified as such, and are returned on request in usable condition.
  • Records. Material certificates, inspection results and approved deviations are kept for as long as the part is in production or service, and supplied on request or on exit.
  • Revision control. Every agreed change becomes a drawing revision through your change process, so the print always matches the part. The engineering change notice guide shows how to run that with an outside supplier.
  • Reference samples. Retain a few approved parts from each new source or new tool as the physical reference for any future remake.
  • Second source on critical parts. For parts whose loss would stop a product, qualify a second source before a crisis rather than after one.

On the RFQ for a remake, say plainly that the part is a resourced, discontinued part, attach the drawing, the model, the sample measurement results and any known gaps between print and part, and ask the new supplier to flag anything it cannot make or measure as written. The RFQ package guide lists the rest.

How is a remake-to-print of a discontinued part handled on a Saola order?

Send the drawing, the model, reference samples or their measurement data, and the quantity you need to bridge or to cover the remaining life. The quote states which plant would make each operation and the country of origin, and comes with a manufacturability note that flags callouts that are unclear or that your sample data contradicts.

Saola Manufacturing is the brand of Aximora Global Trading Co., Ltd., a Ho Chi Minh City company that places and manages metal-parts work; it is not itself a factory. Machined parts are made by CNC turning and CNC milling at our lead CNC plant, T.K Viet Nam Precision Company Limited. Die casting, sand casting, stamping and all surface finishing go to partner plants we manage, which are not named and are not necessarily in Vietnam. Each quote names the production site and the country of origin, so a remade part is never presented as Vietnamese origin unless it is made there.

For a part whose original tooling is being transferred, tell us who owns the tool and send its drawings or photos, so the receiving plant can say whether it can run the tool as it is. For a machined part remade from samples, expect questions about tolerances that the samples cannot answer. ISO 9001 certification is in progress, not held. To start, send the package through the quote form.

Frequently asked

What is the difference between a last time buy and a lifetime buy?

In everyday purchasing the two are often used for the same thing: the final order before a part is discontinued. Some obsolescence literature separates them, treating a lifetime (or life-of-type) buy as covering all expected future demand and a last-time buy as a bridge buy that covers demand only until the next redesign. Agree which one you mean before anyone sizes the order.

Is a last time buy always the cheapest option?

No. It avoids engineering and qualification cost, but it adds storage, capital and the risk of scrapping unused stock. For a long or uncertain remaining need, a bridge buy plus a remake to print often costs less overall.

Can a part be remade to print without the original supplier’s help?

Yes, if you own a complete drawing and have good reference parts. The original supplier’s records and samples make it faster and safer, which is why it pays to ask for them as soon as a discontinuance is likely.

Who owns the tooling when a supplier discontinues a cast or stamped part?

Whoever the contract says owns it. If you paid for the tooling and the purchase order or tooling agreement says it is yours, ask for its return in writing before the supplier closes. If nothing was written, ownership is open to dispute, so settle it early.

Does a remade part need a new first article inspection?

Yes. A new source, plant or tool is a change in how the part is made, so the first lot should be measured against the current drawing and compared with reference parts before the last time buy stock is used up.

Sources

  1. DFARS 252.227-7013, Rights in Technical Data—Other Than Commercial Products and Commercial Services, Defense Federal Acquisition Regulation Supplement (48 CFR), clause dated August 2025
  2. ASME Y14.100, Engineering Drawing Practices, ASME, accessed October 2026
  3. SAE AS9102C, Aerospace Series – First Article Inspection Requirements, SAE International, accessed October 2026
  4. P. Sandborn, “Strategic Management of DMSMS in Systems,” DSP Journal, Defense Standardization Program Office, April/June 2008, pp. 24–30
  5. D. Feng, P. Singh and P. Sandborn, “Lifetime Buy Optimization to Minimize Lifecycle Cost,” Proceedings of the 2007 Aging Aircraft Conference, CALCE, University of Maryland
  6. IEC 62402:2019, Obsolescence management, edition 2.0, International Electrotechnical Commission, May 2019
  7. SAE STD0016A, Standard for Preparing a DMSMS Management Plan, SAE International, December 2023